In Progress
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/22/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Utah
Description:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/01/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
FAST-41 Missed Date:Environmental Assessment (EA): Issuance of a Final EA (Agency Action)
Agency Milestone Date of 05/22/2026 for Issuance of a Final EA (Agency Action) has passed by 1 business days
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/31/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Texas