Permitting Action Modification History

Complete
Section 106 consultation concluded early on June 27, 2024, in advance of the July 1 milestone.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 09-30-2021 09-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 09-30-2021 09-30-2021 --- Yes
Section 106 consultation concluded (Agency Action) 09-26-2023 06-27-2024 --- Yes
In Progress
The basis for BOEM’s request to extend the final completion dates for the Section 106 Consultation is that these actions are dependent upon the timing of BOEM’s issuance of a FEIS and ROD to conclude its NEPA review. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 09-30-2021 09-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 09-30-2021 09-30-2021 --- Yes
Section 106 consultation concluded (Agency Action) 09-26-2023 07-01-2024 --- No
In Progress
Due to delays in receiving revisions to applicant prepared Section 106 documents, the FAST-41 dashboard needs to be updated. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 09-30-2021 09-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 09-30-2021 09-30-2021 --- Yes
Section 106 consultation concluded (Agency Action) 09-26-2023 03-25-2024 --- No
In Progress
The delay is due to lessee not providing a complete and sufficient Section 106 Resources reports: Historic Resources Visual Effects Assessment (HRVEA), Terrestrial Archaeological Resources Assessment (TARA) and Visual Impact Assessment (VIA). Without this data BOEM cannot identify historic properties and assess the effects of the project or conduct necessary Section 106 consultation prior to publication of the draft EIS. Section 106 Consultation must be completed no less than 30 days before the FEIS publication to allow incorporation of the signed MOU into the FEIS. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 09-30-2021 09-30-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 09-30-2021 09-30-2021 --- Yes
Section 106 consultation concluded (Agency Action) 09-26-2023 01-10-2024 --- No