In Progress
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/01/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY

LEAD AGENCY
Texas
FAST-41 Missed Date: Section 106 Review
Final Required Milestone Date of 07/17/2020 for Section 106 consultation concluded has passed by 5 business days
FAST-41 Missed Date: Section 106 Review
Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 01/03/2020 and extended to 07/17/2020
FAST-41 Missed Date: Right-of-Way Authorization (DOI-BLM)
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 08/30/2020 and extended to 12/21/2020
FAST-41 Missed Date: Environmental Impact Statement (EIS)
Triggered missed date from extending Issuance of Lead Agency Record of Decision within 30 days of its current target date which was 07/31/2020 and extended to 11/06/2020