Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-22-2022 04-24-2023 06-15-2023 Yes
ESA Consultation Concludes (Agency Action) 04-24-2023 07-21-2023 02-16-2024 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-22-2022 04-24-2023 06-15-2023 Yes
ESA Consultation Concludes (Agency Action) 04-24-2023 07-21-2023 02-16-2024 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-22-2022 04-24-2023 06-15-2023 Yes
ESA Consultation Concludes (Agency Action) 04-24-2023 07-21-2023 11-10-2023 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-22-2022 04-24-2023 06-15-2023 Yes
ESA Consultation Concludes (Agency Action) 04-24-2023 07-21-2023 10-06-2023 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-22-2022 04-24-2023 05-09-2023 No
ESA Consultation Concludes (Agency Action) 04-24-2023 07-21-2023 10-06-2023 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-22-2022 04-24-2023 05-09-2023 No
ESA Consultation Concludes (Agency Action) 04-24-2023 09-21-2023 10-06-2023 No
Planned
BOEM still needs to submit the final BA and information required to initiate consultation under ESA due partly to delays in receiving analysis from the developer. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-22-2022 04-24-2023 --- No
ESA Consultation Concludes (Agency Action) 04-24-2023 09-21-2023 --- No
Planned
BOEM still needs to submit the final BA and information required to initiate consultation under ESA due partly to delays in receiving analysis from the developer.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-22-2022 04-24-2023 --- No
ESA Consultation Concludes (Agency Action) 04-24-2023 07-21-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 11-22-2022 02-21-2023 --- No
ESA Consultation Concludes (Agency Action) 04-24-2023 07-21-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-29-2022 07-29-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 02-21-2023 02-21-2023 --- No
ESA Consultation Concludes (Agency Action) 07-21-2023 07-21-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 07-15-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- 02-03-2023 --- No
ESA Consultation Concludes (Agency Action) --- 07-06-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 07-15-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- 01-03-2023 --- No
ESA Consultation Concludes (Agency Action) --- 06-02-2023 --- No