Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 11-22-2022 03-23-2023 07-28-2023 Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-23-2023 05-22-2023 10-20-2023 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 11-22-2022 03-23-2023 07-28-2023 Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-23-2023 05-22-2023 10-23-2023 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 11-22-2022 03-23-2023 07-24-2023 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-23-2023 05-22-2023 10-23-2023 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 11-22-2022 03-23-2023 05-24-2023 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-23-2023 05-22-2023 08-23-2023 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 11-22-2022 03-23-2023 05-24-2023 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-23-2023 06-22-2023 08-23-2023 No
Planned
BOEM plans to provide an updated EFH Assessment. Date change allows NOAA sufficient time to review the updated EFH Assessment and determine if all information necessary for the consultation has been provided.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 11-22-2022 03-23-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-23-2023 06-22-2023 --- No
Planned
BOEM plans to provide an updated EFH Assessment. Date change allows NOAA sufficient time to review the updated EFH Assessment and determine if all information necessary for the consultation has been provided.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 11-22-2022 03-23-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-23-2023 05-22-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-01-2022 07-29-2022 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 11-22-2022 02-21-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-23-2023 05-22-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 07-29-2022 07-29-2022 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 02-21-2023 02-21-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 05-22-2023 05-22-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) --- 07-15-2022 --- No
NOAA determines EFH Assessment is Complete (Agency Action) --- 02-03-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) --- 05-04-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) --- 07-15-2022 --- No
NOAA determines EFH Assessment is Complete (Agency Action) --- 01-03-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) --- 04-03-2023 --- No