USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Environmental Assessment (EA)

Submitted by craig.litteken… on

The Applicant recently proposed changes to the project including construction of a new permanent access road, well pad, and injection well in an entirely new footprint, resulting in the loss of approximately 12 additional acres of aquatic resources. USACE must thoroughly evaluate and address the new activities, including the potential associated impacts on federally listed species, proposed compensatory mitigation, and evaluation of cultural and tribal resources.
Additionally, since the Applicant substantially modified the reasonably foreseeable impacts to aquatic resources from those described in the original public notice, USACE determined a new public notice is necessary for proper evaluation of the proposal. To complete the public notice, USACE requested additional information required by regulation. The Applicant stated they will provide the information on November 5, 2025. Once received and determined complete, USACE will issue a public notice describing the modified proposal.

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Status:
In Progress
POC Name:
L. Kasey Sirkin
POC Title:
TREC Team Lead

Milestones:

Determination to prepare an Environmental Assessment (EA) (Agency Action)
Completed Date:
Issuance of a Final EA (Agency Action)
Current Target Date:
EA Process Concluded (Agency Action)
Current Target Date:
Milestone
Issuance of a Final EA (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/03/2027

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Hell’s Kitchen Critical Minerals & Power Project will convert geothermal brine into steam to generate electrical energy.  The power plant will use the geothermal brine to produce electrical power from its steam and the direct lithium extraction plant will convert the dissolved lithium into battery-grade lithium hydroxide and/or lithium carbonate for the battery industry.  The Project is located southeast of the Salton Sea, Calipatria, California.

The Executive Director granted a U.S. Army Corps of Engineers request to extend completion dates for all actions on October 10, 2025.  The Executive Director Determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 09/01/2026
Milestone: Issuance of a Final EA (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of a Final EA (Agency Action) extended by 80
From: 09/01/2026
To: 11/20/2026
Approver Comments
Executive Director Determination signed by Executive Director on 10/10/25.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of a Final EA (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of a Final EA (Agency Action)
Current Target Date: