As part of BLM’s effort to align with the Department of the Interior’s July 15, 2025 memorandum, updates to the Project schedule, including updating the milestone dates on the FAST-41 Dashboard, are necessary to comply with the new requirement that all wind and solar energy project decisions, actions, consultations, and other undertakings be routed through the Office of the Secretary for final review prior to the agency taking action.
The July 15, 2025 Department Memo from the Office of the Secretary requires “all decisions, actions, consultations, and other undertakings—including but not limited to the following—related to wind and solar energy facilities shall require submission to the Office of the Executive Secretariat and Regulatory Affairs, subsequent review by the Office of the Deputy Secretary, and final review by the Office of the Secretary…” These reviews will require additional time during several stages of the environmental process.
The revised schedule extends the BLM’s target dates for issuance of the NEPA document, Section 106 consultation with the Nevada State Historic Preservation Office and Tribes, and the Right-of-Way authorization by approximately nine months. The revised schedule also extends the U.S. Fish and Wildlife Service’s target dates for Section 7 consultation under the Endangered Species Act.
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/06/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Description:
The Silver Star Solar 1 (project) would be entirely on land administered by the Bureau of Land Management (BLM), Southern Nevada District Office (SNDO) in the unincorporated Town of Amargosa Valley, Nye County, Nevada. The proposed project includes construction, operation, maintenance, and decommissioning of a 650 megawatt (MW) alternating current solar photovoltaic power generating facility with a 650 MW battery energy storage system on approximately 3,005 acres. The solar generation field would be located approximately five miles south of U.S. Highway 95 and six miles west of State Highway 373. Death Valley National Park is approximately four miles southwest of the Project. The proposed Project would be on Solar Variance lands as identified in the 2012 Final Programmatic Environmental Impact Statement for Solar Energy Development in Six Southwestern States (Solar PEIS).
The Executive Director granted a Bureau of Land Management request to extend the Right-of-Way Authorization, NEPA, and ESA-FWS completion dates on December 20, 2024. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Land Management request to extend the Right-of-Way Authorization, NEPA, and ESA-FWS completion dates on July 9, 2025. The Executive Director determination is posted here.
Original Target Date: 01/16/2026
Milestone: Final decision/agency action (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Final decision/agency action (Agency Action) extended by 689
From: 01/27/2027
To: 12/06/2027