USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Section 106 Review

Submitted by giannina.dimai… on

As part of BLM’s effort to align with the Department of the Interior’s July 15, 2025 memorandum, updates to the Mosey Solar Project schedule, including updating the milestone dates on the FAST-41 Dashboard, are necessary to comply with the new requirement that all wind and solar energy project decisions, actions, consultations, and other undertakings be routed through the Office of the Secretary for final review prior to the agency taking action.

The July 15, 2025 Department Memo from the Office of the Secretary requires “all decisions, actions, consultations, and other undertakings—including but not limited to the following—related to wind and solar energy facilities shall require submission to the Office of the Executive Secretariat and Regulatory Affairs, subsequent review by the Office of the Deputy Secretary, and final review by the Office of the Secretary…” These reviews will require additional time during several stages of the environmental process.

The revised schedule extends the BLM’s target dates for issuance of the NEPA document, Section 106 consultation with the Nevada State Historic Preservation Office and Tribes, and the Right-of-Way authorization by approximately fifteen months. The revised schedule also extends the U.S. Fish and Wildlife Service’s target dates for Section 7 consultation under the Endangered Species Act.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
In Progress
POC Name:
Tiffany Arend
POC Title:
District Archaeologist
POC Email:
SHPO:

Nevada

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/18/2028

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

Clearway Energy Group LLC proposes to construct a 500-megawatt (MW) solar photovoltaic (PV) power generating facility and battery storage facility with up to 850 MW of battery energy storage.  The Project would be sited entirely on approximately 3,568 acres of public land administered by the U.S. Bureau of Land Management (BLM) in Pahrump Valley, Nevada.  The Project would interconnect to the existing Trout Canyon Substation located approximately 3 miles from the Mosey Solar project area. 

The Executive Director granted, in part, and denied, in part, a Bureau of Land Management request to extend the Right-of-Way Authorization, Section 106, NEPA, and ESA-FWS completion dates on November 13, 2025. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 08/06/2027
Milestone: Section 106 consultation concluded (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Section 106 consultation concluded (Agency Action) extended by 318
From: 08/06/2027
To: 06/19/2028
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date: