Milestone Extension: Environmental Assessment (EA)
The applicant delayed sending the Site-Specific Plan of Development 6 (SPOD-6) until May 23, 2019. The project Sponsor (Proponent, Power Company of Wyoming) is make business decisions to ensure that their transmission line (Transwest Express) is on a similar construction timeline. Currently, the Chokecherry Sierra Madre Project is under construction on Phase I and the haul road and infrastructure for Phase II. The proponent has permitting in place to allow for construction for all of the 2019 construction season.