FAST-41 Missed Date: Section 404 Clean Water Act
Final Required Milestone Date of 09/15/2020 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 09/15/2020 for Final Verification/Permit Decision Rendered has passed by 5 business days
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 08/28/2020 and extended to 09/08/2020
FWS originally requested an extension from 8/28 to 9/18 based on communication with the Project Sponsor on the time it would need to sign the final permit; however, the Project Sponsor returned the final ROW permit and payment to FWS on 9/4/2020 and the FWS Regional Director executed it on 9/8/2020.
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 08/07/2020 and extended to 09/30/2020
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 07/13/2020 and extended to 08/21/2020
Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 07/17/2020 and extended to 07/28/2020
Final Required Milestone Date of 05/22/2020 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 05/12/2020 for Section 106 consultation concluded has passed by 5 business days
Final Required Milestone Date of 05/08/2020 for Issuance of Lead Agency Record of Decision has passed by 5 business days
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 11/12/2019 and extended to 05/23/2021