Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by carlos_arandia on

This date has been revised in accordance with OED email dated 2/27/2019.

Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/05/2019

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of Energy

Department of Energy, Office of Fossil Energy

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

This project consists of two proposals:  Venture Global Calcasieu Pass Terminal (Docket No. CP15-550-000) and TransCameron Pipeline (Docket Nos. CP15-551-000 and CP15-551-001).  The project consists of:  (1) the addition of 1.4 Bcf/d through construction of a new LNG export terminal in Louisiana; and (2) construction of a 23.4-mile-long natural gas pipeline and associated meter station in Louisiana, to provide 1.9 Bcf/d of natural gas transportation service at the LNG terminal for export.

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed. 

 

State Agency Permitting Timetable for Venture Global Calcasieu Pass Terminal and TransCameron Pipeline Project 
Responsible State Agency Federal Permit/Review Intermediate Completion Date Final Completion Date Description Field
Louisiana Department of Natural Resources, Office of Coastal Management Section 307 CZMA Review N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
Louisiana Department of Environmental Quality, Water Permits Division Section 401 CWA Review - Water Quality Certification N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  Water quality certification issued within 90 days after application is determined to be administratively complete.
Louisiana Department of Environmental Quality, Water Permits Division Section 402 CWA Review - National Pollutant Discharge Elimination System, Stormwater General Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  Per state regulations, the Louisiana Department of Environmental Quality (LDEQ) has 300 days from receipt of an application to review and issue a water discharge permit.  LDEQ follows the 300 day timetable for review and issuance of water discharge permits.
Louisiana Department of Environmental Quality, Water Permits Division Section 402 CWA Review - National Pollutant Discharge Elimination System, Industrial Wastewater Discharge Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  Per state regulations, the Louisiana Department of Environmental Quality (LDEQ) has 300 days from receipt of an application to review and issue a water discharge permit.  LDEQ follows the 300 day timetable for review and issuance of water discharge permits.
Louisiana Department of Environmental Quality, Water Permits Division Section 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge Permit N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  Per state regulations, the Louisiana Department of Environmental Quality (LDEQ) has 300 days from receipt of an application to review and issue a water discharge permit.  LDEQ follows the 300 day timetable for review and issuance of water discharge permits.
Louisiana Department of Environmental Quality, Air Permits Division Title V CAA Review - Operating Permit for Air Emissions N/A TBD The state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."

 

 

Last updated March 7, 2019

field_status
System Comments
Furthest out Original Target Date: 10/01/2018
Milestone: Final Verification/Permit Decision Rendered

Requested extensions greater than 30 days for this Action are shown below:

Final Verification/Permit Decision Rendered by 137 days
From: 12/19/2018
To: 02/15/2019
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date: