USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Submitted by carlos_arandia on

Justification due to internal agency factors - in perfecting the legal land description of the ROW grant.

Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Riley Ridge to Natrona Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/10/2019

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Riley Ridge to Natrona Project (Project) consists of three right-of-way grant applications:  (1) the Riley Ridge Carbon Dioxide (CO2) Pipeline Project, (2) the Bairoil to Natrona CO2 Pipeline Project, and (3) right-of-way for a 230-kilovolt (kV) transmission line to supply energy to the proposed Riley Ridge Sweetening Plant. It is a 243-mile project crossing through Fremont, Sublette, Sweetwater and Natrona counties in Wyoming on federal, state and private lands (191 miles on BLM lands). If approved, the Project would include the proposed Riley Ridge Sweetening Plant where H2S would be separated from the CO2 stream and injected into a deep geological formation via two proposed adjacent hydrogen sulfide (H2S) injection wells.

As proposed, the Riley Ridge to Sweeting Plant segment would include 31 miles of 16-inch pipeline transporting liquid H2S and CO2 from the existing Riley Ridge Treating Plant located 18 miles southwest of Big Piney, Wyoming, to the proposed Riley Ridge Sweetening Plant to be located 12 miles northeast of LaBarge, Wyoming. From the proposed Riley Ridge Sweetening Plant, a 24-inch pipeline would transport liquid CO2 129 miles through Sublette and Sweetwater counties to the Bairoil Interconnect located 50 miles northwest of Rawlins, Wyoming. The Bairoil to Natrona segment would include 83 miles of 24-inch pipeline transporting liquid CO2 from the Bairoil Interconnect through Fremont and Natrona counties to the Greencore Pipeline at the Natrona Hub 30 miles west of Casper, Wyoming.

field_status
System Comments
Furthest out Original Target Date: 03/30/2018
Milestone: Issuance of decision for permit/approval

Requested extensions greater than 30 days for this Action are shown below:

Issuance of decision for permit/approval by 376 days
From: 01/22/2019
To: 04/10/2019
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final decision/agency action (Agency Action)
Current Target Date: