USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by carlos_arandia on

The Corps is requesting an extension of the FPL Turkey Point project from April 22, 2019 until May 22, 2019. A Department of the Army permit cannot be issued until we receive: A complete mitigation plan. A request for additional information was sent to the applicant on February 26, 2019 and the applicant provided a response March 19, 2019. The Corps will need the extension to review the information and incorporate it into the record of decision. The Corps (Regulatory) cannot issue a permit until the mitigation is finalized. Should submittal of any required information be delayed, the Corps will adjust its timeline accordingly.

Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: http://www.nrc.gov/reactors/new-reactors/col/turkey-point.html

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/18/2019

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production

SECTOR
Conventional Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Nuclear Regulatory Commission

LEAD AGENCY
Nuclear Regulatory Commission, Office of New Reactors

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The USACE proffered the remaining permit to the project sponsor (Florida Power and Light) December 18, 2019.

Florida Power and Light Company (FPL), seeks approval for constructing and operating two new AP1000 reactor units at the Turkey Point site to provide additional electricity for use in the Southern Florida service areas.  The two new units would be capable of providing an additional 2200 megawatts of baseload electricity.

field_status
System Comments
Furthest out Original Target Date: 10/22/2018
Milestone: Final Verification/Permit Decision Rendered

Requested extensions greater than 30 days for this Action are shown below:

Final Verification/Permit Decision Rendered by 212 days
From: 04/22/2019
To: 05/22/2019
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date: