Project sponsor is aware of delay and is working with Navy to complete the NHPA Section 106 and Tribal Consultations by June 30. Date change does not affect the permitting timetable as it is not on the critical path. DoD CERPO has been informed and understands that project sponsor & the Navy have significant participatory roles in getting consultations completed.
There are no milestones to display.
PROJECT WEBSITE: Boardman To Hemingway Project Page
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/10/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Electricity Transmission
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:

Department of Defense, US Navy
Department of Agriculture, US Forest Service
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Bureau of Reclamation
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Description:
PacifiCorp, Bonneville Power Administration (BPA), and Idaho Power jointly propose to design, construct, operate and maintain a new 500 kilovolt, single-circuit electric transmission line from a proposed substation near Boardman, Oregon to the Hemingway Substation near Melba, Idaho. The 500kV line will span approximately 300 miles total, 88 miles on land managed by the Bureau of Land Management (BLM). The project would provide additional capacity for exchanging energy between the Pacific Northwest and the Intermountain West, depending on which region is experiencing the highest demand.
BLM received Idaho Power Company’s Boardman to Hemingway Transmission Line Project application and Plan of Development (POD) on Dec. 19, 2007.
In keeping with its mission and NEPA, BLM has established collaborative relationships with many Federal, State and local organizations to facilitate cooperative government reviews, ensure science-based decision-making, and prevent duplicative efforts. As part of this approach, BLM incorporates input from the public and affected local governments into the review process. BLM relies on this input to develop an Environmental Impact Statement (as required by 30 CFR 550.269) to support its decision-making process. Additional information, including NEPA documentation, can be found on the Boardman to Hemingway project page, http://boardmantohemingway.com.
Project Litigation - A complaint was filed with the United States District Court for the District of Oregon, Pendleton Division on 11/12/2019, Case 2:19-cv-01822-SU
There are no milestones to display.
There are no milestones to display.
Milestone: Notice to proceed
Requested extensions greater than 30 days for this Action are shown below:
Issuance of decision for permit/approval by 61 days
From: 12/31/2018
To: 07/31/2019
Notice to proceed by 61 days
From: 05/31/2019
To: 07/31/2019