Approved

Milestone Extension: Section 404 Clean Water Act

The lead Federal agency has indicated that delays have occurred in NHPA compliance, and identified via email on September 26, 2019, that they recommend a revised target date of January 31, 2020, for the decision.

Milestone Extension: Environmental Impact Statement (EIS)

The target date has now changed a week from the original date of 1/3 to 1/17 due to a partial lapse in government funding, earlier this year. Proponent is aware and tailored their submittal of applications to cooperating agencies with the 1/17 date in mind. All are aware of this change and are in support of this schedule.

Milestone Extension: Section 106 Review

Execution of the 106 Programmatic Agreement was delayed pending proposed changes requested by one of the consulting parties. The project sponsor changed the date accordingly for the conclusion of the 106 PA and the Record of Decision which will not be issued on December 6, 2019. Issues were not included in the most recent quarterly CPP. The CERPO has been made aware. These delays will not have any significant impact on the project.

Milestone Extension: Marine Mammal Protection Act (MMPA) Incidental Take Authorization – DOC - NOAA/NMFS

While the current extension request from 12/1/19 to 12/31/19 for publication of the final rule is greater than 30 days from the ORIGINAL date, it is less than 30 days from the currently published target date for this milestone. As a reminder, the schedule was adjusted in fall 2018 to better align with the applicant's (Hillcorp) revised permitting and construction timeline for the project, which extended the construction schedule by at least one year.