The project sponsor requested the EFH milestones be revised to allow for additional time to conduct the EFH Assessment.
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/24/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of Commerce, National Oceanic and Atmospheric Administration
Description:
The Graphite Creek Project is a proposed graphite open pit mine to extract graphite ore and produce a graphite concentrate for further processing and manufacturing of Coated Spherical Graphite, primarily for the electric vehicle lithium-ion battery and energy storage markets, as well as other high grade graphite products. Graphite ore mined from the Graphite Creek Property, situated on the Seward Peninsula about 37 miles north of Nome, Alaska, would be processed into concentrate at a mineral processing plant to be located adjacent to the mine.
Original Target Date: 03/20/2026
Milestone: NOAA Issues any EFH Conservation Recommendations (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
NOAA Issues any EFH Conservation Recommendations (Agency Action) extended by 149
From: 03/20/2026
To: 08/16/2026