FAST-41 Missed Date:Endangered Species Act Consultation (DOI-FWS): FWS determines ESA Consultation Package is Complete - Informal (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 08/22/2025 for FWS determines ESA Consultation Package is Complete - Informal (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Status:
Planned
POC Name:
Holly Carroll
POC Title:
Acting Field Supervisor, Northern Alaska Fish and Wildlife Office

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
FWS determines ESA Consultation Package is Complete - Informal (Agency Action)
Current Target Date:
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone
FWS determines ESA Consultation Package is Complete - Informal (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: https://www.nanabroadband.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/15/2026

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Commerce

LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration

View FAST-41 Postings by Agencies

Description:

The NANA Regional Corporation, Inc. proposes to implement a high-speed broadband network in the NANA region through the Tribal Broadband Connectivity Program. The proposed ~725-mile fiber optic cable route consists of a combination of terrestrial ground-laid, subsea, trenched, and aerial cable to connect villages across vast distances to the broadband Point of Presence in Kotzebue. The Project plans to bring a fiber-based broadband network capable of providing high-speed internet services to Alaska Native Villages in the NANA Region.

field_status
System Comments
Agency Milestone Date of 08/22/2025 for FWS determines ESA Consultation Package is Complete - Informal (Agency Action) has passed by 1 business days
Approver Comments
Milestone was met on time and published complete
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
FWS determines ESA Consultation Package is Complete - Informal (Agency Action)
Current Target Date:
Response Date