Project sponsor indicated a revised application will be submitted in June. Timeline adjusted accordingly. See milestone description for additional information.
There are no milestones to display.
PROJECT WEBSITE: http://penneastpipeline.com
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/27/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Description:
PennEast Pipeline (Docket No. CP15-558-000) would provide an additional 1.0 Bcf/d of natural gas transportation service through construction of: (1) 115.1 miles of pipeline from Pennsylvania to New Jersey; (2) 2.1 miles of various lateral pipelines; and (3) a new compressor station.
Project Application and Supporting Documents
- PennEast Pipeline, Project Application, Volume I, FERC Docket No. CP15-558-000 (submitted 09/25/2015). Document located at: http://elibrary.ferc.gov/IDMWS/common/OpenNat.asp?fileID=13995667.
- PennEast Pipeline, Supporting Documents to Project Application, FERC Docket No. CP15-558-000 (submitted 09/25/2015). Documents located at: http://elibrary.ferc.gov/IDMWS/search/intermediate.asp?link_file=yes&doclist=14380457.
- Additional Project-related filings and issuances can be found on FERC’s eLibrary website by searching under Docket Nos. CP15-558.
Federal Agency Actions
- Federal Energy Regulatory Commission, Notice of Schedule for Environmental Review of the PennEast Pipeline Project (issued 03/29/2016). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14182825.
- Federal Energy Regulatory Commission, Draft Environmental Impact Statement (issued 07/22/2016). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14314021.
- Federal Energy Regulatory Commission, Notice of Revised Schedule for Environmental Review of the PennEast Pipeline Project (issued 11/08/2016). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14394276.
- Federal Energy Regulatory Commission, Notice of Revised Schedule for Environmental Review of the PennEast Pipeline Project (issued 1/23/2017). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=14470112.
- Federal Energy Regulatory Commission, Final Environmental Impact Statement (issued 04/07/2017). Document available at: https://cms.ferc.gov/final-environmental-impact-statement-penneast-pipeline-project.
- Federal Energy Regulatory Commission, Order Issuing Certificate (issued 01/19/2018). Document located at: https://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14801473.
FERC Litigation
- None filed.
Last updated March 27, 2021
There are no milestones to display.
There are no milestones to display.