USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Endangered Species Act Consultation (NOAA-NMFS)

Submitted by carlos_arandia on

NA

Milestone

There are no milestones to display.

Project

PROJECT WEBSITE: https://www.boem.gov/Liberty/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production

SECTOR
Conventional Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of War Seal

Department of War, US Army Corps of Engineers - Regulatory

Description:

Hilcorp proposes to develop the Liberty Prospect in Foggy Island Bay, Beaufort Sea, Alaska by constructing an artificial drilling and production gravel island, approximately 6 miles offshore. The proposed Liberty Development described in the Development and Production Plan includes five stages: construction of the island; development of a new gravel mine; construction of a pipeline; construction of associated ice roads; and drilling and hydrocarbon production.

The island will have drilling and production processing facilities, with a single phase oil pipeline transmitting the produced sales-quality oil to shore. The island will include 16 well slots: 5-8 producers, 4-6 injectors, 2 disposal wells. Hilcorp estimates that peak production will be approximately 60,000 - 70,000 barrels per day. Estimated first production may occur in 2020-2021. The project life is estimated to be 15-20 years, with a total recovery estimate of about 167 million barrels.

Associated Permitting:

Environmental Protection Agency - NPDES Permit: Completed 10/26/2018, available here: https://www.epa.gov/npdes-permits/npdes-permit-hilcorp-alaska-liberty-drilling-and-production-island

Bureau of Safety and Environmental Enforcement - Oil Spill Response Plan: Returned to Hilcorp July 2019 with a Request For Additional Information (RFAI) 

Bureau of Safety and Environmental Enforcement - Platform Approval Program and Platform Verification Program: Approval timeline dependent upon Oil Spill Response Plan Approval

Bureau of Safety and Environmental Enforcement - Application for Permit to Drill: Approval timeline dependent upon Oil Spill Response Plan Approval 

Bureau of Safety and Environmental Enforcement - Production Safety Systems Permitting: Approval timeline dependent upon Oil Spill Response Plan Approval 

Note: The project timeline represents the cooperating agencies' estimates at when agency actions could occur depending on the project proponent's future submissions. 

field_status
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone

There are no milestones to display.

Furthest Original Target Date Milestone

There are no milestones to display.