Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by craig.litteken… on

The completion date for USACE’s Section 10/404 permit decision is dependent on the completion date for the NEPA action and is being extended to be concurrent with finalization of the EA.

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Carolyn Farmer
POC Title:
Project Manager

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Current Target Date:
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Current Target Date:
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: The Alaska FiberOptic Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/16/2024

5 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Commerce

LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

The Alaska FiberOptic Project Segment 1 proposes to deploy a reliable, affordable, scalable and future-proofed broadband network bridging the digital divide for the foreseeable future in one of the most remote, isolated, high-cost, and difficult to serve areas of the United States. The Alaska FiberOptic Project Segment 1 is one phase of a 3-phase project that includes constructing a middle mile fiber optic network (under water and on land) directly supporting last mile high-speed Internet connections to 23 Alaskan Native Villages along the Yukon River. The Alaska Fiber Optic Project Segment 1 would begin by connecting to existing fiber in Fairbanks, Alaska and use existing utility line easements to bury cable. The route would travel along the Steese Highway, Elliott and Dalton highways to the E.L. Patton Yukon River Bridge. From the E.L. Patton Bridge the cable would be laid in the active channel of the Yukon River upstream to Ft. Yukon and downstream to Tanana.

field_status
System Comments
Furthest out
Original Target Date: 06/10/2024
Milestone: Final Verification/Permit Decision Rendered (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final Verification/Permit Decision Rendered (Agency Action) extended by 59
From: 06/10/2024
To: 08/08/2024
Approver Comments
Executive Director Determination signed on 2/29/24.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date: