USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Environmental Impact Statement (EIS)

Submitted by cori.carraway@… on

The project sponsor’s delayed submission of information needed for a complete Marine Mammal
Protection Act (MMPA) Incidental Take Authorization (ITA) application has resulted in delays to the
schedule for NMFS’s issuance of the proposed ITA as well as delays to the development of complete
Endangered Species Act (ESA) and Essential Fish Habitat (EFH) consultation documents, the Draft
Environmental Impact Statement (DEIS), the Final Environmental Impact Statement (FEIS) and all other
subsequent dependent milestones. BOEM developed an updated permitting timetable reflecting the
90-day shift to the DEIS, FEIS, and Record of Decision (ROD) milestone dates. The NEPA Action is
impacted by the milestone shifts for the ESA Action as a result of the shifts for the MMPA Action; the
NEPA timeline is changing accordingly. See the explanation for the MMPA milestone shifts for more
information.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Bonnie L Houghton
POC Title:
NEPA Coordinator
Public Participation Website:

Description:

Beacon Wind proposes to develop the entire Lease Area into two separate wind projects, known as Beacon Wind 1 (BW1) and Beacon Wind 2 (BW2). Offshore components of the Beacon Wind Project would consist of up to 155 wind turbines and up to 2 offshore substation facilities for a total of up to 157 foundations. The 157 foundations would be spaced one nautical mile by one nautical mile apart in fixed east-west rows and north-south columns. In addition, there would be up to 324 nautical miles of inter-array cable, all of which will be located in federal waters within the Lease Area. Renewable energy produced by BW1 would be delivered onshore via an up to 202 nautical-mile submarine export cable making landfall in Queens, New York. Renewable energy produced by BW2 would be delivered onshore via an up to 202 nautical-mile submarine export cable making landfall in either Queens, New York, or an up to 113 nautical-mile submarine export cable making landfall in Waterford, Connecticut. Onshore components of the Project would include submarine cable landfall areas, onshore export and interconnection cables, and onshore substation facilities.

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Beacon Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/27/2026

0 out of 11

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Environmental Protection Agency

Environmental Protection Agency

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

Beacon Wind proposes to construct and operate an offshore wind farm to be located approximately 20 statute miles (mi) (17 nautical miles [nm], 32 kilometers [km]) south of Nantucket, Massachusetts, and 60 mi (52 nm, 97 km) east of Montauk, New York. Offshore components of the Project will consist of up to 155 wind turbines and up to two offshore substation facilities for a total of up to 157 foundations.

Update:

The Executive Director granted a Bureau of Ocean Energy Management request to extend the NEPA, COP, Section 106, ESA-FWS, ESA-NMFS, EFH, MMPA, Section 10/404, Section 408, OCS air permit and NPDES permit completion dates on March 15, 2024. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 07/01/2025
Milestone: Issuance of Lead Agency Record of Decision (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of Lead Agency Record of Decision (Agency Action) extended by 90
From: 07/01/2025
To: 09/29/2025
Approver Comments
EDD signed 3/15/2024
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date: