USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Approved

Milestone Extension: Section 404 Clean Water Act

A detailed justification and information on consultation with the affected cooperating agencies and project sponsor are included in Commission staff’s request for Executive Director determination submitted to FPISC-OED via email.  Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents, are being modified to account for the additional time needed for the

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

A detailed justification and information on consultation with the affected cooperating agencies and project sponsor are included in Commission staff’s request for Executive Director determination submitted to FPISC-OED via email.  Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents, are being modified to account for the additional time needed for the

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

A detailed justification and information on consultation with the affected cooperating agencies and project sponsor are included in Commission staff’s request for Executive Director determination submitted to FPISC-OED via email.  Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents, are being modified to account for the additional time needed for the

Milestone Extension: Lease of Power Privilege (DOI-BOR)

A detailed justification and information on consultation with the affected cooperating agencies and project sponsor are included in Commission staff’s request for Executive Director determination submitted to FPISC-OED via email.  Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents, are being modified to account for the additional time needed for the

Milestone Extension: NPS Permit

In addition to interagency delays in developing project alternatives in June 2022, the project sponsor presented new project information in February 2023, to BOEM, NOAA, and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 22 WTGs for the project due to glauconite sands present within the Lease Area. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS.

Milestone Extension: Clean Water Act Section 402 Permit, National Pollutant Discharge Elimination System (EPA)

In addition to interagency delays in developing project alternatives in June 2022, the project sponsor presented new project information in February 2023, to BOEM, NOAA, and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 22 WTGs for the project due to glauconite sands present within the Lease Area. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS.

Milestone Extension: Section 408 Permit

Issuance of Decision milestone change:

BOEM presented a 3rd revised schedule to the cooperating agencies on 4/20/23, which included  delays to the DEIS and ROD due to feasibility issues with turbine generator foundations and subsequent updates to consultation and ROD milestones.