Milestone Extension: Outer Continental Shelf (OCS) Air Permit
Extension of 91 days needed beyond the ROD for EPA’s OCS air permit decision
Extension of 91 days needed beyond the ROD for EPA’s OCS air permit decision
The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10), and installation of splice vaults and duct banks, and the expansion of an existing substation (Phase 1B activities, scheduled to commence around September).
The basis for USACE requests to extend the final completion date for the Section 408
Permit is that these actions are dependent upon the timing of BOEM’s issuance of a FEIS and ROD to conclude its NEPA review.
Agency Milestone Date of 01/31/2024 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10),
The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10),
The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10),
The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10),
The project sponsor provided BOEM notice on June 26, 2023 of plans to initiate onshore construction activities. The notice provided information on their planned work at the Onshore Converter Station and laydown yards (Phase 1A activities, scheduled to start around July 10),
The basis for BOEM’s request to extend the final completion dates for the Section 106
Consultation is that these actions are dependent upon the timing of BOEM’s issuance of a FEIS and ROD to conclude its NEPA review.