Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act
The date has been changed as per BOEM's revised schedule. The date change was coordinated the lead agency, BOEM.
The date has been changed as per BOEM's revised schedule. The date change was coordinated the lead agency, BOEM.
On Feb 8, 2023, NOAA filed the proposed rule for the Sunrise Wind Offshore Wind Project in the Federal Register for public comment. The Dashboard has been updated to mark this milestone "complete".
In addition to interagency delays in developing project alternatives in June 2022, the project sponsor presented new project information in February 2023, to BOEM, NOAA, and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 22 WTGs for the project due to glauconite sands present within the Lease Area. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS.
In addition to interagency delays in developing project alternatives in June 2022, the project sponsor presented new project information in February 2023, to BOEM, NOAA, and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 22 WTGs for the project due to glauconite sands present within the Lease Area. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS.
In addition to interagency delays in developing project alternatives in June 2022, the project sponsor presented new project information in February 2023, to BOEM, NOAA, and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 22 WTGs for the project due to glauconite sands present within the Lease Area. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS. The project design changed the impacts analysis for consultations.
Applicant delays caused delay in EPA’s application completeness determination, which shifted final decision milestone date forward according to the one-year statutory deadline under CAA § 165.
The date for publication of the final ITA regulations was revised due to the revised EIS schedule. The final ITA regulations cannot be published until the ROD is published, so had to be revised to be after the new ROD publication date. In addition the final MMPA milestone was revised due to the required 30-day period after the final ITA regulations are published.
The project sponsor presented new project information last fall on October 13, 2022, to BOEM, NOAA,
and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 21 WTGs for the project. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS. The project design changed the impacts analysis for consultations. This action is dependent upon the ROD.
The project sponsor presented new project information last fall on October 13, 2022, to BOEM, NOAA,
and USACE. The change in design for feasible wind turbine generator (WTG) locations involved removing 21 WTGs for the project. This change required additional analysis by BOEM for a new constructible preferred alternative that needed to be added to FEIS. The project design changed the impacts analysis for consultations.
The United States Army Corps of Engineers (USACE), on behalf of the Coastal Protection and Restoration Authority, (Applicant/Project Sponsor), is requesting time extensions for all the planned and in-progress target milestone dates on the permitting dashboard for the Applicant’s Mid-Breton Sediment Diversion project. This revised schedule is d