Approved

Milestone Extension: Section 106 Review

The United States Army Corps of Engineers (USACE), on behalf of the Coastal Protection and Restoration Authority, (Applicant/Project Sponsor), is requesting time extensions for all the planned and in-progress target milestone dates on the permitting dashboard for the Applicant’s Mid-Breton Sediment Diversion project.  This revised schedule is d

Milestone Extension: Environmental Impact Statement (EIS)

The United States Army Corps of Engineers (USACE), on behalf of the Coastal Protection and Restoration Authority, (Applicant/Project Sponsor), is requesting time extensions for all the planned and in-progress target milestone dates on the permitting dashboard for the Applicant’s Mid-Breton Sediment Diversion project.  This revised schedule is d

Milestone Extension: Section 408 Permit

The United States Army Corps of Engineers (USACE), on behalf of the Coastal Protection and Restoration Authority, (Applicant/Project Sponsor), is requesting time extensions for all the planned and in-progress target milestone dates on the permitting dashboard for the Applicant’s Mid-Breton Sediment Diversion project.  This revised schedule is d

Milestone Extension: Endangered Species Act Consultation (NOAA-NMFS)

The United States Army Corps of Engineers (USACE), on behalf of the Coastal Protection and Restoration Authority, (Applicant/Project Sponsor), is requesting time extensions for all the planned and in-progress target milestone dates on the permitting dashboard for the Applicant’s Mid-Breton Sediment Diversion project.  This revised schedule is d

Milestone Extension: Construction and Operations Plan

The Delay to the DEIS due to the sponsor not providing sufficient documents , and revisions to the project design envelope as late as 3/13/2023 that requires the COP end date to move as the ROD (Under the EIS milestone) must be issued before the COP agency decision can be made.