Agency Milestone Date of 02/23/2024 for EFH Consultation Request Submitted – EFH Assessment (Agency Action) has passed by 1 business days
Cooperating under NEPA
Milestones:
PROJECT WEBSITE: Beacon Wind
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Description:
Beacon Wind proposes to construct and operate an offshore wind farm to be located approximately 20 statute miles (mi) (17 nautical miles [nm], 32 kilometers [km]) south of Nantucket, Massachusetts, and 60 mi (52 nm, 97 km) east of Montauk, New York. Offshore components of the Project will consist of up to 155 wind turbines and up to two offshore substation facilities for a total of up to 157 foundations.