USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Section 106 Review

Submitted by cori.carraway@… on

Section 106 consultation is being conducted through the Section 106 NEPA substitution process and is interrelated with the NEPA timeline which is changing.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Marissa Moshier
POC Title:
Historian

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Atlantic Shores Offshore Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/11/2027

0 out of 11

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

No icon

Department of Defense, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

Atlantic Shores Offshore Wind, LLC (“Atlantic Shores”) proposes to construct, operate, and maintain the Atlantic Shore North Project (the “Project”; “Atlantic Shores North”), an offshore renewable wind energy facility in Lease Area OCS-A 0549, which is approximately 7.8 statute miles (mi) (12.6 kilometers [km]) from the New Jersey (NJ) shoreline and approximately 60 miles (96.6 km) from the New York State (NY) Coast.

The Lease Area layout is designed to maximize offshore renewable wind energy production while minimizing effects on existing marine uses. The structures will be aligned in a uniform grid with multiple lines of orientation allowing straight transit through the Lease Area. Within the Lease Area, the WTGs and OSSs will be connected by inter-array cables and/or inter-link cables. Energy from the OSSs will be delivered to shore by buried export cables that will be located within designated Export Cable Corridors (ECCs) from the Lease Area through Federal as well as New Jersey and/or New York State waters to landfall sites on the New Jersey and/or New York coastlines.

Atlantic Shores will use horizontal directional drilling (HDD) technology to install the export cables from the end of the ECCs to the landfall sites to minimize impacts to the intertidal and nearshore habitats and ensure stable burial of the cables. From each landfall site, the onshore interconnection cables will travel underground primarily along existing roadways and utility rights-of-way (ROWs) to new or existing onshore substation and/or converter station sites.

field_status
System Comments
Furthest out
Original Target Date: 05/20/2026
Milestone: Section 106 consultation concluded (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Section 106 consultation concluded (Agency Action) extended by 147
From: 05/20/2026
To: 10/14/2026
Approver Comments
EDD completed 1/2/2025
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date: