USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Endangered Species Act Consultation (NOAA-NMFS)

Submitted by cori.carraway@… on

The interim milestone, “ESA Consultation Package Submitted” is aligned with the date BOEM submits the draft DEIS for cooperating agency review and is dependent on NMFS receiving a consultation request from BOEM (as lead Federal agency), consisting of a draft Biological Assessment, that considers effects of all proposed Federal actions.

The interim milestone, “NOAA Determines ESA Package is Complete,” is dependent upon NMFS receiving sufficient information from BOEM and the other Federal action agencies to deem the package complete and initiate the ESA consultation. This includes receipt of: a complete final Biological Assessment responding to any previous information requests, the final draft or published proposed MMPA Incidental Take Authorization from NMFS OPR, and the public availability of the DEIS.  This milestone is aligned with the MMPA milestone for publication of the proposed ITA, as the publication date of the proposed ITA is when we anticipate that all of the information necessary to initiate the ESA consultation would be available. This is consistent with the nominal timeline for OSW.

The final Milestone, “ESA Consultation Concludes,” must be at least 150 days after determining the ESA package complete (135 day regulatory timeline plus 15 days to allow for BOEM review of the draft Opinion).  Note that the Milestone date for publication of the Final EIS date must allow for adequate time for incorporation of the findings of the ESA consultation into the Final EIS.

Action
Project Name: Responsible Agency:
National Oceanic and Atmospheric Administration
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
  • Monthly Status Report for June 2025:
    Project paused until January 2026 consultations will resume when project restarts.
  • Monthly Status Report for May 2025:
    BOEM is on track to meet the milestone completion date.
  • Monthly Status Report for April 2025:
    BOEM is on track to meet the milestone completion date.  
  • Non-conformance Explanation:
    BOEM was unable to conform with this milestone for Atlantic Shores North (ASOW N) due to uncertainty in the project timeline.  The Presidential Memorandum, Temporary Withdrawal of All Areas on the Outer Continental Shelf from Offshore Wind Leasing and Review of the Federal Government’s Leasing and Permitting Practices for Wind Projects, discusses the development of a comprehensive assessment and review of Federal wind leasing and permitting practices.  Further guidance as to how the assessment will impact the project is necessary to conform to this milestone.
Current Target Date:
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Atlantic Shores Offshore Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/11/2027

0 out of 11

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

No icon

Department of Defense, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

Atlantic Shores Offshore Wind, LLC (“Atlantic Shores”) proposes to construct, operate, and maintain the Atlantic Shore North Project (the “Project”; “Atlantic Shores North”), an offshore renewable wind energy facility in Lease Area OCS-A 0549, which is approximately 7.8 statute miles (mi) (12.6 kilometers [km]) from the New Jersey (NJ) shoreline and approximately 60 miles (96.6 km) from the New York State (NY) Coast.

The Lease Area layout is designed to maximize offshore renewable wind energy production while minimizing effects on existing marine uses. The structures will be aligned in a uniform grid with multiple lines of orientation allowing straight transit through the Lease Area. Within the Lease Area, the WTGs and OSSs will be connected by inter-array cables and/or inter-link cables. Energy from the OSSs will be delivered to shore by buried export cables that will be located within designated Export Cable Corridors (ECCs) from the Lease Area through Federal as well as New Jersey and/or New York State waters to landfall sites on the New Jersey and/or New York coastlines.

Atlantic Shores will use horizontal directional drilling (HDD) technology to install the export cables from the end of the ECCs to the landfall sites to minimize impacts to the intertidal and nearshore habitats and ensure stable burial of the cables. From each landfall site, the onshore interconnection cables will travel underground primarily along existing roadways and utility rights-of-way (ROWs) to new or existing onshore substation and/or converter station sites.

field_status
System Comments
Furthest out
Original Target Date: 02/03/2026
Milestone: ESA Consultation Concludes (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

ESA Consultation Concludes (Agency Action) extended by 146
From: 02/03/2026
To: 06/29/2026
Approver Comments
EDD completed 1/2/2025
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date: