Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-10-2022 08-08-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 12-20-2022 03-01-2023 04-27-2023 Yes
ESA Consultation Concludes (Agency Action) 05-30-2023 07-17-2023 09-28-2023 Yes
In Progress
BOEM informed NOAA that they are delaying submittal of the revised BA by two weeks.  BOEM and NOAA agreed to a corresponding two-week shift in milestone dates to allow for review of the revised BA before determining complete and two-week shift in the conclusion of the ESA consultation resulting in this delay.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-10-2022 08-08-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 12-20-2022 03-01-2023 04-27-2023 Yes
ESA Consultation Concludes (Agency Action) 05-30-2023 07-17-2023 09-28-2023 No
Planned
BOEM informed NOAA that they are delaying submittal of the revised BA by two weeks.  BOEM and NOAA agreed to a corresponding two-week shift in milestone dates to allow for review of the revised BA before determining complete and two-week shift in the conclusion of the ESA consultation resulting in this delay.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-10-2022 08-08-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 12-20-2022 03-01-2023 --- No
ESA Consultation Concludes (Agency Action) 05-30-2023 07-17-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-10-2022 08-08-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 12-20-2022 02-16-2023 --- No
ESA Consultation Concludes (Agency Action) 05-30-2023 07-17-2023 --- No
Planned
This dashboard milestone date change is interagency driven.  A delay in the development of alternatives analysis has led to a delay in the distribution of the PDEIS for cooperating agency review. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-11-2022 08-08-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 01-19-2023 02-16-2023 --- No
ESA Consultation Concludes (Agency Action) 06-29-2023 07-17-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-11-2022 07-11-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 01-19-2023 01-19-2023 --- No
ESA Consultation Concludes (Agency Action) 06-29-2023 06-29-2023 --- No