USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-10-2022 08-08-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 12-20-2022 03-01-2023 04-27-2023 Yes
ESA Consultation Concludes (Agency Action) 05-30-2023 07-17-2023 09-28-2023 Yes
In Progress
BOEM informed NOAA that they are delaying submittal of the revised BA by two weeks.  BOEM and NOAA agreed to a corresponding two-week shift in milestone dates to allow for review of the revised BA before determining complete and two-week shift in the conclusion of the ESA consultation resulting in this delay. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-10-2022 08-08-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 12-20-2022 03-01-2023 04-27-2023 Yes
ESA Consultation Concludes (Agency Action) 05-30-2023 07-17-2023 09-28-2023 No
Planned
BOEM informed NOAA that they are delaying submittal of the revised BA by two weeks.  BOEM and NOAA agreed to a corresponding two-week shift in milestone dates to allow for review of the revised BA before determining complete and two-week shift in the conclusion of the ESA consultation resulting in this delay.  
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-10-2022 08-08-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 12-20-2022 03-01-2023 --- No
ESA Consultation Concludes (Agency Action) 05-30-2023 07-17-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-10-2022 08-08-2022 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 12-20-2022 02-16-2023 --- No
ESA Consultation Concludes (Agency Action) 05-30-2023 07-17-2023 --- No
Planned
This dashboard milestone date change is interagency driven.  A delay in the development of alternatives analysis has led to a delay in the distribution of the PDEIS for cooperating agency review.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-11-2022 08-08-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 01-19-2023 02-16-2023 --- No
ESA Consultation Concludes (Agency Action) 06-29-2023 07-17-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-11-2022 07-11-2022 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 01-19-2023 01-19-2023 --- No
ESA Consultation Concludes (Agency Action) 06-29-2023 06-29-2023 --- No