Permitting Action Modification History

In Progress
Given that the Corps had adopted the BOEM EIS to inform our decision-making process and because the evaluation of environmental considerations may change as a result of BOEM’s review of the EIS, the Corps cannot finalize a decision until BOEM’s reconsideration of the EIS is complete. To accommodate BOEM’s review of the EIS, the Corps is moving the current FAST-41 milestone from April 9, 2026, to October 9, 2026., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 10-09-2026 No
In Progress
The Corps acknowledges the December 18, 2025 decision of the U.S. District Court for the District of Massachusetts in State of New York, et al. v. Trump, et al., 1:25-cv-11221 (D. Mass.) regarding the validity of multiple agencies’ pause on permitting wind projects pursuant to section 2(a) of the January 20, 2025 Presidential Memorandum on “Temporary Withdrawal of All Areas on the Outer Continental Shelf from Offshore Wind Leasing and review of the Federal Government’s Leasing and Permitting Practices for Wind Projects.” However, before that decision was issued, the Bureau of Ocean Energy Management (BOEM) sought in separate litigation to reevaluate its decision on the SouthCoast Wind project due to a change in interpretation of 43 U.S.C. § 1337(p)(4) and an interim determination that the Environmental Impact Statement (EIS) and other documents that BOEM prepared may have “understated or obfuscated impacts that could have subsequently been improperly weighed in making the determinations” under § 1337(p)(4). BOEM Motion for Voluntary Remand, Town & County of Nantucket v. Burgum, et al., No. 1:25-cv-00906, Doc. 21 at 7 (D.D.C. Sep. 18, 2025) (citation and internal quotation marks omitted). The U.S. District Court for the District of Columbia granted the motion and remanded BOEM’s decision for further review on November 4, 2025. Nantucket, No. 1:25-cv-00906-TSC, 2025 WL 3120419 (D.D.C. Nov. 4, 2025). Given that the Corps had adopted the BOEM EIS to inform our decision making process and because the evaluation of environmental considerations may change as a result of BOEM’s review of the EIS, the Corps cannot finalize a decision until BOEM’s reconsideration of the EIS is complete. To accommodate the time necessary to coordinate with BOEM regarding BOEM’s review of the EIS, the Corps is moving the current FAST-41 milestone from January 9, 2026 to April 9, 2026.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 04-09-2026 No
In Progress
USACE, as a cooperating agency for this project, is providing an updated alternative completion date for the final permit milestone for the subject project under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act.  The current alternative completion date on the dashboard is September 24, 2025. Pursuant to the Presidential Memorandum, Temporary Withdrawal of All Areas on the Outer Continental Shelf From Offshore Wind Leasing and Review of the Federal Government’s Leasing and Permitting Practices for Wind Projects, USACE is unable to render the final permit at this time. Therefore, to sync our alternative completion date with other agency milestones, USACE has identified an alternative completion date of January 9, 2026, and will continually reassess the schedule based on Administration directives.  The New England District coordinated this date with the project Sponsor.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 01-09-2026 No
In Progress
USACE, as a cooperating agency for this project, is providing an updated alternative completion date for the final permit milestone for the subject project under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act.  The current alternative completion date on the dashboard is June 26, 2025. Pursuant to the Presidential Memorandum, Temporary Withdrawal of All Areas on the Outer Continental Shelf From Offshore Wind Leasing and Review of the Federal Government’s Leasing and Permitting Practices for Wind Projects, USACE is unable to render the final permit at this time. Therefore, to sync our alternative completion date with the current effort to draft an Executive Director Determination for milestone modification for other agency milestones, USACE has identified an alternative completion date of September 24, 2025, and will continually reassess the schedule based on Administration directives.  The New England District coordinated this date with the project Sponsor.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 09-24-2025 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 06-26-2025 No
In Progress
The Section 10/404 final milestone date is dependent upon the completion of BOEM’s NEPA action (i.e., ROD issuance). For this Project, the USACE review will require 90 days between issuance of the ROD and issuance of USACE’s Section 10/404 decision. Therefore, an extension of the Section 10/404 final milestone date is requested based upon the extension of the ROD milestone date.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 03-27-2025 No
In Progress
Update: the final milestone had been revised to reflect the revised BOEM schedule, the new ROD date is Dec 8, 2023. The new final permit decision rendered date is March 7, 2024.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 --- No
In Progress
Update: the milestone had been revised to reflect the revised BOEM schedule, the new ROD date is Dec 8, 2023. The new final permit decision rendered date is March 7, 2024.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 --- No
Planned
Change was coordinated with BOEM in Sept 2022. Due to delays from the finalization of the alternatives, as well as delays related to the LOA application process, BOEM has had to delay the overall schedule. This is simply a data entry update to reflect the corrected decision date based on BOEM's changes.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- No
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 --- No
Planned
Dates updated as part of Original Target Dates data entry effort. Dates updated to reflect delay caused by the finalization of alternatives.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-28-2022 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- No
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 --- No