USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 06-26-2025 No
In Progress
The Section 10/404 final milestone date is dependent upon the completion of BOEM’s NEPA action (i.e., ROD issuance). For this Project, the USACE review will require 90 days between issuance of the ROD and issuance of USACE’s Section 10/404 decision. Therefore, an extension of the Section 10/404 final milestone date is requested based upon the extension of the ROD milestone date.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 03-27-2025 No
In Progress
Update: the final milestone had been revised to reflect the revised BOEM schedule, the new ROD date is Dec 8, 2023. The new final permit decision rendered date is March 7, 2024.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 --- No
In Progress
Update: the milestone had been revised to reflect the revised BOEM schedule, the new ROD date is Dec 8, 2023. The new final permit decision rendered date is March 7, 2024.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- Yes
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 --- No
Planned
Change was coordinated with BOEM in Sept 2022. Due to delays from the finalization of the alternatives, as well as delays related to the LOA application process, BOEM has had to delay the overall schedule. This is simply a data entry update to reflect the corrected decision date based on BOEM's changes.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-02-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- No
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 --- No
Planned
Dates updated as part of Original Target Dates data entry effort. Dates updated to reflect delay caused by the finalization of alternatives.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-30-2022 12-28-2022 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-15-2022 02-02-2023 --- No
Publication of Public Notice (Agency Action) 12-30-2022 02-17-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 01-25-2024 01-25-2024 --- No