Milestone Extension: Environmental Impact Statement (EIS)
Original Entry was Data Entry Error
Original Entry was Data Entry Error
The applicant accepted terms of Forest Service special use permit (SUP) on December 14, 2017. SUP terms required completion of certain actions before construction activity can begin on National Forest System lands including: execution of NHPA programmatic agreement, State approval of erosion & sediment control plans and stormwater management plans, a determination by USFWS regarding impacts to candy darter, and finalize timber sale contract.
Per e-mail correspondence with Amber Levofsky on 6/27/17, the project sponsor has Paused the review.
The project sponsor has paused this permit review. As such we are marking the permit as Paused, and changing the target date. Amber Levofsky confirmed via e-mail dated 6/27/17 that this permit/milestone should be paused.
The date change is a result of internal agency processing. These are the final milestones for the project and no other adjustments are needed. The applicant has been informed of the date change.
delay due to lapse in appropriations
waiting for project sponsor to submit final POD
We did not previously have a target date for our target completion date (our 4th and last milestone), or target dates for our 2nd and 3rd milestones, so there is nothing to extend beyond 30 days. As such, I am not sure why this notification is popping up. I marked the "reason for change" date as "Updating Planned Date". I was under the impression from the last Dashboard Administrator meeting that updating planned dates do not require FPISC OED review, even if planned completion dates would be extended more than 30 days. It would be very helpful to get clarification on this.
The DEIS has been delayed due to additional analysis required to address mitigation concerns. DOI has identified a new target completion date for the DEIS and is expediting the remaining permitting milestones accordingly, which includes issuing the ROD and ROW concurrently.