FAST-41 Missed Date:Section 404 Clean Water Act: Publication of Public Notice (Agency Action)
Agency Milestone Date of 10/19/2019 for Publication of Public Notice (Agency Action) has passed by 1 business days
Agency Milestone Date of 10/19/2019 for Publication of Public Notice (Agency Action) has passed by 1 business days
Triggered missed date from extending Completeness determination (Agency Action) within 30 days of its current target date which was 08/03/2022 and extended to 08/15/2022
Final Required Milestone Date of 03/09/2021 for Issuance of decision for permit/approval (Agency Action) has passed by 5 business days
Final Required Milestone Date of 01/08/2021 for Completeness determination (Agency Action) has passed by 5 business days
Final Required Milestone Date of 06/15/2022 for Issuance of decision for permit/approval has passed by 5 business days
Final Required Milestone Date of 06/15/2022 for Final Verification/Permit Decision Rendered (Cooperating/Participating Agency Action) has passed by 5 business days
Extension requested due to sponsor factors and approved via memo.
Entire project has been delayed due to delayed acoustic modeling results and LOA submission to NOAA.
Final Required Milestone Date of 05/30/2022 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 05/29/2022 for Issuance of decision for permit/approval has passed by 5 business days