Final Required Milestone Date of 06/15/2022 for Final Verification/Permit Decision Rendered (Cooperating/Participating Agency Action) has passed by 5 business days
Cooperating under NEPA
Description:
The Corps 404 permit action was cancelled on the Dashboard in March 2022 due to FERC’s dismissal, without prejudice, of the license application for the LEAPs project, which became a final Commission action on March 24, 2022.
Milestones:
This milestone date is dependent on the applicant's submittal of a pre-construction notification/application package notification by the given target date of 3/11/2021. The Corps coordinated with the Applicant on 9/18/2020.
This milestone date is dependent on the applicant's submittal of a complete pre-construction notification/application package notification by the given target date of 1/30/2022. The Corps last coordinated with the Applicant on 10/28/2021.
-
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
-
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 12/22/2021 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 03/17/2022 -
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 03/17/2022
This milestone is dependent on the applicant's submittal of a complete preconstruction notification by the target date for milestone 2, as well as the applicant's timely submittal of information of any information that may be necessary for a verification decision. This milestone is also dependent upon the completion of the Section 7 Endangered Species Act and Section 106 National Historic Preservation Act consultations by FERC as the lead Federal agency, and completion of a 401 water quality certification or waiver from the CA State Water Quality Control Board. The milestone is dependent upon the issuance of a Section 408 permission by the Corps, should it be required. In general, to obtain a Section 404 permit, the Applicant must demonstrate that the discharge of dredged or fill material would not significantly degrade the nation's waters and there are no practicable alternatives less damaging to the aquatic ecosystem, so long as the alternative does not have other significant adverse environmental consequences. The Applicant should also describe steps taken to minimize impacts to water bodies and wetlands and provide appropriate and practicable mitigation, such as restoring or creating wetlands, for any remaining, unavoidable impacts. If a standard individual permit is required, the Applicant will be required to provide sufficient information for the Corps to assure compliance with Section 404(b)(1) Guidelines, including information for the Corps' alternative analysis to identify the Least Environmentally Damaging Practicable Alternative (LEDPA). The analysis of impacts to WoUS will include direct, indirect, and cumulative effects. Should compensatory mitigation be required for unavoidable impacts to the aquatic environment, this milestone will be dependent on the Applicant providing a compensatory mitigation plan for Corps' approval.
-
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
-
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 12/22/2021 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 03/17/2022 -
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 03/17/2022
This milestone is dependent on the applicant's submittal of a complete preconstruction notification by the target date for milestone 2, as well as the applicant's timely submittal of information of any information that may be necessary for a verification decision. This milestone is also dependent upon the completion of the Section 7 Endangered Species Act and Section 106 National Historic Preservation Act consultations by FERC as the lead Federal agency, and completion of a 401 water quality certification or waiver from the CA State Water Quality Control Board. The milestone is dependent upon the issuance of a Section 408 permission by the Corps, should it be required. In general, to obtain a Section 404 permit, the Applicant must demonstrate that the discharge of dredged or fill material would not significantly degrade the nation's waters and there are no practicable alternatives less damaging to the aquatic ecosystem, so long as the alternative does not have other significant adverse environmental consequences. The Applicant should also describe steps taken to minimize impacts to water bodies and wetlands and provide appropriate and practicable mitigation, such as restoring or creating wetlands, for any remaining, unavoidable impacts. If a standard individual permit is required, the Applicant will be required to provide sufficient information for the Corps to assure compliance with Section 404(b)(1) Guidelines, including information for the Corps' alternative analysis to identify the Least Environmentally Damaging Practicable Alternative (LEDPA). The analysis of impacts to WoUS will include direct, indirect, and cumulative effects. Should compensatory mitigation be required for unavoidable impacts to the aquatic environment, this milestone will be dependent on the Applicant providing a compensatory mitigation plan for Corps' approval.
PROJECT WEBSITE: LEAPS Hydropower
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Description:
The Lake Elsinore Advanced Pumped Storage Project (Project No. 14227) is a proposal to construct an original pumped storage project in California. The proposed project would consist of: (1) a new upper reservoir (Decker Canyon) having a 200-foot-high main dam and a gross storage volume of 5,750 acre-feet, at a normal reservoir surface elevation of 2,792 feet above mean sea level; (2) a powerhouse with two reversible pump-turbine units with a total installed capacity of 500 megawatts; (3) the existing Lake Elsinore to be used as a lower reservoir; (4) about 32 miles of 500-kilovolt transmission line connecting the project to an existing transmission line owned by Southern California Edison located north of the proposed project and to an existing San Diego Gas & Electric Company transmission line located to the south.
On December 9, 2021, Commission staff issued a letter dismissing, without prejudice, the license application for the project. On January 7, 2022, the project sponsor filed a request for rehearing or, in the alternative, motion for temporary stay of dismissal of license application. On March 24, 2022, the Commission issued an order sustaining the result of the December 9, 2021 order and denying the motion for temporary stay.
FAST-41 Initiation Notice
- Document located at: https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20200708-3026.
Project Application and Supporting Documents
- Lake Elsinore Advanced Pumped Storage Project, Transmittal Letter for Final License Application (filed 10/02/2017). Document located at: https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20171002-0008.
- Lake Elsinore Advanced Pumped Storage Project, Final License Application (filed 10/02/2017). Document located at: https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20171002-4003.
- Additional project-related filings can be found on FERC’s eLibrary website by searching under Docket No. P-14227.
Federal Agency Actions
- Federal Energy Regulatory Commission, Notice of Application Tendered for Filing with the Commission and Soliciting Additional Study Requests (issued 10/11/2017). Document located at: https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20171011-3023.
- Federal Energy Regulatory Commission, Notice of Application Accepted for Filing and Soliciting Motions to Intervene and Protests (issued 07/26/2019). Document located at: https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20190726-3008.
- Federal Energy Regulatory Commission, Notice of Intent to Prepare an Environmental Impact Statement and Soliciting Scoping Comments (issued 06/18/2020). Document located at: https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20200618-3007.
- Federal Energy Regulatory Commission, Letter Dismissing License Application (issued 12/09/2021). Document located at: https://elibrary.ferc.gov/eLibrary/filedownload?fileid=3A8024DF-717D-CFDA-95D0-7DA014000000.
- Federal Energy Regulatory Commission, Order Addressing Arguments Raised on Rehearing and Denying Motion for Temporary Stay (issued 03/24/2022). Document located at: https://elibrary.ferc.gov/eLibrary/filedownload?fileid=75D17F3A-3719-CB60-9591-7FBCE8100000.
- Additional project-related issuances can be found on FERC’s eLibrary website by searching under Docket No. P-14227.
Status of Mitigation Measures
- Not applicable. On March 24, 2022, the Commission issued an order sustaining the result of the December 9, 2021 order dismissing the license application for the project.
FERC Litigation
- None filed.
Public Meetings and Comment Periods
- There are no planned public meetings or comment periods. On March 24, 2022, the Commission issued an order sustaining the result of the December 9, 2021 order dismissing the license application for the project.
Last updated March 29, 2022
-
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
-
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Current Target Date: 12/22/2021 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Current Target Date: 03/17/2022 -
Environmental Impact Statement (EIS)
:
Issuance of Lead Agency Record of Decision (Agency Action)
- Current Target Date: 03/17/2022
This milestone is dependent on the applicant's submittal of a complete preconstruction notification by the target date for milestone 2, as well as the applicant's timely submittal of information of any information that may be necessary for a verification decision. This milestone is also dependent upon the completion of the Section 7 Endangered Species Act and Section 106 National Historic Preservation Act consultations by FERC as the lead Federal agency, and completion of a 401 water quality certification or waiver from the CA State Water Quality Control Board. The milestone is dependent upon the issuance of a Section 408 permission by the Corps, should it be required. In general, to obtain a Section 404 permit, the Applicant must demonstrate that the discharge of dredged or fill material would not significantly degrade the nation's waters and there are no practicable alternatives less damaging to the aquatic ecosystem, so long as the alternative does not have other significant adverse environmental consequences. The Applicant should also describe steps taken to minimize impacts to water bodies and wetlands and provide appropriate and practicable mitigation, such as restoring or creating wetlands, for any remaining, unavoidable impacts. If a standard individual permit is required, the Applicant will be required to provide sufficient information for the Corps to assure compliance with Section 404(b)(1) Guidelines, including information for the Corps' alternative analysis to identify the Least Environmentally Damaging Practicable Alternative (LEDPA). The analysis of impacts to WoUS will include direct, indirect, and cumulative effects. Should compensatory mitigation be required for unavoidable impacts to the aquatic environment, this milestone will be dependent on the Applicant providing a compensatory mitigation plan for Corps' approval.