USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Approved

Milestone Extension: Section 106 Review

The Corps and the federal cooperating agencies, along with CPRA (the applicant), have been working diligently to prepare the Final Environmental Impact Statement (FEIS) for CPRA’s proposed Mid-Barataria Sediment Diversion (MBSD) Project.  The MBSD is a large and complex project.  The proposed project would discharge up to 75,000 cfs of sediment, freshwater, and nutrients within the Barataria Basin.  The total cost is estimated at more than $1 billion and faces many environmental and engineering challenges due to

Milestone Extension: Environmental Impact Statement (EIS)

The Corps and the federal cooperating agencies, along with CPRA (the applicant), have been working diligently to prepare the Final Environmental Impact Statement (FEIS) for CPRA’s proposed Mid-Barataria Sediment Diversion (MBSD) Project.  The MBSD is a large and complex project.  The proposed project would discharge up to 75,000 cfs of sediment, fres

Milestone Extension: Section 408 Permit

The Corps and the federal cooperating agencies, along with CPRA (the applicant), have been working diligently to prepare the Final Environmental Impact Statement (FEIS) for CPRA’s proposed Mid-Barataria Sediment Diversion (MBSD) Project.  The MBSD is a large and complex project.  The proposed project would discharge up to 75,000 cfs of sediment, freshwater, and nutrients within the Barataria Basin.  The total cost is estimated at more than $1 billion and faces many environmental and engineering challenges due to

Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

The Corps and the federal cooperating agencies, along with CPRA (the applicant), have been working diligently to prepare the Final Environmental Impact Statement (FEIS) for CPRA’s proposed Mid-Barataria Sediment Diversion (MBSD) Project.  The MBSD is a large and complex project.  The proposed project would discharge up to 75,000 cfs of sediment, freshwater, and nutrients within the Barataria Basin.  The total cost is estimated at more than $1 billion and faces many environmental and engineering challenges due to