Milestone Extension: Section 106 Review
Extension requested due to sponsor factors and approved via memo.
Extension requested due to sponsor factors and approved via memo.
Entire project has been delayed due to delayed acoustic modeling results and LOA submission to NOAA.
Final Required Milestone Date of 05/30/2022 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 05/29/2022 for Issuance of decision for permit/approval has passed by 5 business days
Final Required Milestone Date of 05/30/2022 for Section 106 consultation concluded has passed by 5 business days
There was a data entry error.
The Corps and the federal cooperating agencies, along with CPRA (the applicant), have been working diligently to prepare the Final Environmental Impact Statement (FEIS) for CPRA’s proposed Mid-Barataria Sediment Diversion (MBSD) Project. The MBSD is a large and complex project. The proposed project would discharge up to 75,000 cfs of sediment, freshwater, and nutrients within the Barataria Basin. The total cost is estimated at more than $1 billion and faces many environmental and engineering challenges due to
The Corps and the federal cooperating agencies, along with CPRA (the applicant), have been working diligently to prepare the Final Environmental Impact Statement (FEIS) for CPRA’s proposed Mid-Barataria Sediment Diversion (MBSD) Project. The MBSD is a large and complex project. The proposed project would discharge up to 75,000 cfs of sediment, fres
The Corps and the federal cooperating agencies, along with CPRA (the applicant), have been working diligently to prepare the Final Environmental Impact Statement (FEIS) for CPRA’s proposed Mid-Barataria Sediment Diversion (MBSD) Project. The MBSD is a large and complex project. The proposed project would discharge up to 75,000 cfs of sediment, freshwater, and nutrients within the Barataria Basin. The total cost is estimated at more than $1 billion and faces many environmental and engineering challenges due to
The Corps and the federal cooperating agencies, along with CPRA (the applicant), have been working diligently to prepare the Final Environmental Impact Statement (FEIS) for CPRA’s proposed Mid-Barataria Sediment Diversion (MBSD) Project. The MBSD is a large and complex project. The proposed project would discharge up to 75,000 cfs of sediment, freshwater, and nutrients within the Barataria Basin. The total cost is estimated at more than $1 billion and faces many environmental and engineering challenges due to