USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by danny.wiegand@… on

Milestone updated as per BOEM's revised schedule and ROD date of October 23, 2023. USACE decision date is scheduled for 120 days after the BOEM ROD.

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Christopher Minck
POC Title:
Project Manager

Description:

Department of Army authorization from the US Army Corps of Engineers New York District is required pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act.  Activities that require authorization include: Installation of turbine structures on monopile foundations or gravity base structures (GBS) foundations embedded in the ocean floor. Installation of export cable(s) and associated cable protection. Installation of inter-array cables between turbine structures and offshore substations. Monopile or jacket pile supported offshore substation(s). Horizontal directional drilling or open cut trenching along the shoreline for the export cable to begin its path to a substation/grid connection. 

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Completed Date:
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Completed Date:
Publication of Public Notice (Agency Action)
Completed Date:
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Equinor's Empire Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/11/2024

10 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

Equinor Wind proposes to construct and operate the Empire Wind Energy Project located in Lease Area OCS-A 0512, which covers approximately 79,350 acres (ac; 32,112 hectares [ha]) and is located approximately 14 statute miles (mi) (12 nautical miles [nm], 22 kilometers [km]) south of Long Island, New York and 19.5 mi (16.9 nm, 31.4 km) east of Long Branch, New Jersey.

 

field_status
System Comments
Furthest out
Original Target Date: 09/11/2023
Milestone: Final Verification/Permit Decision Rendered (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final Verification/Permit Decision Rendered (Agency Action) extended by 162
From: 09/11/2023
To: 02/20/2024
Approver Comments
ED Determination of extension finalized, 3/23/23, approved.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date: