FAST-41 Missed Date:Section 408 Permit: Issuance of decision for permit/approval (Agency Action)
Final Required Milestone Date of 03/09/2021 for Issuance of decision for permit/approval (Agency Action) has passed by 5 business days
Final Required Milestone Date of 03/09/2021 for Issuance of decision for permit/approval (Agency Action) has passed by 5 business days
Final Required Milestone Date of 01/08/2021 for Completeness determination (Agency Action) has passed by 5 business days
Final Required Milestone Date of 06/15/2022 for Issuance of decision for permit/approval has passed by 5 business days
Final Required Milestone Date of 06/15/2022 for Final Verification/Permit Decision Rendered (Cooperating/Participating Agency Action) has passed by 5 business days
Extension requested due to sponsor factors and approved via memo.
Entire project has been delayed due to delayed acoustic modeling results and LOA submission to NOAA.
Final Required Milestone Date of 05/30/2022 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 05/29/2022 for Issuance of decision for permit/approval has passed by 5 business days
Final Required Milestone Date of 05/30/2022 for Section 106 consultation concluded has passed by 5 business days
There was a data entry error.