USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Authorization and Certification

Submitted by craig.litteken… on

Notified by BOEM that ROD dates has changed and Executive Director approval is required. Updated USACE decision dates based on BOEM's changes to ROD date. USACE decision dates remains at 90 days post-ROD. 

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Civil Works
Agency Status: Cooperating under FAST-41
Status:
In Progress
POC Name:
Courtney Colwell
POC Title:
Realty Specialist

Description:

An outgrant from USACE Norfolk District Real Estate Office, if needed.

Milestones:

Initial application received (Applicant Action)
Completed Date:
Completed application received (Applicant Action)
Completed Date:
Issuance of decision for permit/approval (Agency Action
Current Target Date:
Milestone
Issuance of decision for permit/approval (Agency Action
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/09/2024

11 out of 11

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Environmental Protection Agency

Environmental Protection Agency

Description:

Dominion Energy is proposing to construct, own, and operate the Coastal Virginia Offshore Wind (CVOW) Commercial Project (the Project). The Project will be located in the Commercial Lease of Submerged Lands for Renewable Energy Development on the Outer Continental Shelf Offshore Virginia (Lease No. OCS-A-0483) (Lease Area). The Lease Area, located within Official Protraction Diagram NJ18-11 Currituck Sound, covers approximately 112,799 acres (45,658 hectares) and is approximately 27 statute miles (23.75 nautical miles, 43.99 kilometers) off the Virginia Beach coastline.

FAST-41 provides increased transparency and predictability by requiring Federal agencies to publish comprehensive permitting timetables for all "covered" projects, and provides clear procedures for modifying permitting timetables to address the unpredictability inherent in the environmental review and permitting process for significant infrastructure projects. For more information, see "The FAST-41 Process" at  https://www.permits.performance.gov/fpisc-content/fast-41-process. 

field_status
System Comments
Furthest out
Original Target Date: 08/31/2023
Milestone: Issuance of decision for permit/approval (Agency Action

Requested extensions greater than 30 days for this Action are shown below:

Issuance of decision for permit/approval (Agency Action extended by 151
From: 08/31/2023
To: 01/29/2024
Approver Comments
ED Determination of extension granted on 03/30/23, via signed memo.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of decision for permit/approval (Agency Action
Current Target Date:
Furthest Original Target Date Milestone
Issuance of decision for permit/approval (Agency Action
Current Target Date: