Section 106 Review

Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
Complete
POC Name:
Christopher Horrell
POC Title:
Historic Preservation Officer
Action Outcome:
Executed memorandum of agreement or programmatic agreement or other conclusion to resolve adverse effects reached

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
  • Monthly Status Report for November 2023:
    On track to meet the alternative completion date of Nov 21. BOEM is awaiting final signature on MOA.
  • Monthly Status Report for October 2023:
    On track to meet alternative completion date of Nov 21, 2023.
  • Non-conformance Explanation:
    BOEM is utilizing the NEPA substitution process to conduct the consultation, which aligns the consultation schedule with the NEPA process. BOEM determined the need to move the Section 106 milestone during the lockout period to align it with a new ROD milestone target. The additional time also allowed BOEM to honor a request by Consulting parties, including the Advisory Council on History Preservation and several tribes, for additional time to review the proposed mitigations due to their extensive nature.
Alternative Completion Date: