USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
Final permit decision for EW1 rendered ahead of schedule. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-29-2022 10-03-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-29-2022 11-03-2022 --- Yes
Publication of Public Notice (Agency Action) 11-18-2022 11-07-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-11-2023 03-11-2024 --- Yes
In Progress
Milestone updated as per BOEM's revised ROD date. BOEM ROD date shifted from October 23 2023 to November 21 2023 and the USACE final milestone has been adjusted accordingly. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-29-2022 10-03-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-29-2022 11-03-2022 --- Yes
Publication of Public Notice (Agency Action) 11-18-2022 11-07-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-11-2023 03-20-2024 --- No
In Progress
Milestone updated as per BOEM's revised schedule and ROD date of October 23, 2023. USACE decision date is scheduled for 120 days after the BOEM ROD.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-29-2022 10-03-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-29-2022 11-03-2022 --- Yes
Publication of Public Notice (Agency Action) 11-18-2022 11-07-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-11-2023 02-20-2024 --- No
In Progress
The public notice was published early, in advance of the DEIS NOA, to provide 30 days notice for the public hearings, as per Corps regulations. Target date was 11/18/22. Actual publication date was 11/7/22, ahead of schedule.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-29-2022 10-03-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-29-2022 11-03-2022 --- Yes
Publication of Public Notice (Agency Action) 11-18-2022 11-07-2022 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-11-2023 09-11-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-29-2022 10-03-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-29-2022 11-03-2022 --- Yes
Publication of Public Notice (Agency Action) 11-18-2022 11-18-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-11-2023 09-11-2023 --- No
Planned
Original Target Date Data Entry Effort
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-29-2022 10-03-2022 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 07-29-2022 11-03-2022 --- No
Publication of Public Notice (Agency Action) 11-18-2022 11-18-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-11-2023 09-11-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 10-03-2022 10-03-2022 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 11-03-2022 11-03-2022 --- No
Publication of Public Notice (Agency Action) 11-18-2022 11-18-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-11-2023 09-11-2023 --- No