Endangered Species Act Consultation (DOI-FWS)

Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Participating
Status:
Complete
POC Name:
Ian Drew
POC Title:
Field Supervisor
POC Email:
Action Outcome:
Biological opinion issued

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Completed Date:
ESA Consultation Concludes (Agency Action)
  • Non-conformance Explanation:
    The milestone was extended to 6/26/23 because new information was received in a BA addendum on 3/28/23, and the USFWS requested  more time to incorporate the new information into the Biological Opinion.  
Alternative Completion Date: