Environmental Impact Statement (EIS)

Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
Complete
POC Name:
Brandi Sangunett
POC Title:
Environmental Protection Specialist
Action Outcome:
Issuance of a joint ROD

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Completed Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
  • Monthly Status Report for November 2023:
    On track to meet the alternative completion date of Nov 21, 2023. Awaiting execution of Sec 106 MOA prior to issuance of ROD.
  • Monthly Status Report for October 2023:
    On track to meet the alternative completion date of Nov 21, 2023
  • Non-conformance Explanation:
    BOEM’s FEIS must incorporate measures resulting from Sec 7 consultations. The prior milestone date for publication of the FEIS was Sep 8. ​​​​​NMFS concluded ESA consultation on Sep 8 with issuance of the Biological Opinion, with reasonable and prudent measures (RPMs), terms and conditions, and conservation recommendations. BOEM needed an additional week to analyze and incorporate the NMFS recommendations into the FEIS. BOEM published the FEIS on Sep 15.
Alternative Completion Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Alternative Completion Date: