Triggered missed date from extending Completed application received (Agency Action) within 30 days of its current target date which was 11/21/2025 and extended to 05/02/2026
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/05/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
Clearway Energy Group LLC proposes to construct a 500-megawatt (MW) solar photovoltaic (PV) power generating facility and battery storage facility with up to 850 MW of battery energy storage. The Project would be sited entirely on approximately 3,568 acres of public land administered by the U.S. Bureau of Land Management (BLM) in Pahrump Valley, Nevada. The Project would interconnect to the existing Trout Canyon Substation located approximately 3 miles from the Mosey Solar project area.