USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Mosey Solar Project

PERMITTING DASHBOARD PROJECT POSTING DATE: JANUARY 17, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Planned

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Description:

Clearway Energy Group LLC proposes to construct a 500-megawatt (MW) solar photovoltaic (PV) power generating facility and battery storage facility with up to 850 MW of battery energy storage.  The Project would be sited entirely on approximately 3,568 acres of public land administered by the U.S. Bureau of Land Management (BLM) in Pahrump Valley, Nevada.  The Project would interconnect to the existing Trout Canyon Substation located approximately 3 miles from the Mosey Solar project area. 

Permitting Timetable

Planned Environmental Review and Permitting processes