FAST-41 Missed Date:Right-of-Way Authorization (DOI-BLM): Completed application received (Agency Action)
Agency Milestone Date of 11/17/2025 for Completed application received (Agency Action) has passed by 1 business days
Agency Milestone Date of 11/17/2025 for Completed application received (Agency Action) has passed by 1 business days
Agency Milestone Date of 11/17/2025 for Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) has passed by 1 business days
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/01/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Highway Administration
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/29/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of Defense, US Air Force
Triggered missed date from extending Completed application received (Agency Action) within 30 days of its current target date which was 11/21/2025 and extended to 05/02/2026