Bureau of Land Management
FAST-41 Missed Date:Right-of-Way Authorization (DOI-BLM): Completed application received (Agency Action)
Agency Milestone Date of 07/01/2025 for Completed application received (Agency Action) has passed by 1 business days
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Description:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/09/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Description:
FAST-41 Missed Date:Environmental Impact Statement (EIS): Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Agency Milestone Date of 06/13/2025 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days