FAST-41 Missed Date:Use Authorization (DOI-BOR): Application deemed complete (Agency Action)
Agency Milestone Date of 09/18/2026 for Application deemed complete (Agency Action) has passed by 1 business days
Agency Milestone Date of 09/18/2026 for Application deemed complete (Agency Action) has passed by 1 business days
Agency Milestone Date of 09/15/2026 for Section 106 consultation concluded (Agency Action) has passed by 1 business days
Agency Milestone Date of 08/12/2026 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
Agency Milestone Date of 08/11/2026 for ESA Consultation Request Package Submitted (Agency Action) has passed by 1 business days
Agency Milestone Date of 08/07/2026 for Issuance of Lead Agency Record of Decision (Agency Action) has passed by 1 business days
Agency Milestone Date of 08/07/2026 for Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) has passed by 1 business days
Agency Milestone Date of 08/07/2026 for Issuance of decision for Mine Plan of Operations (Agency Action) has passed by 1 business days
Agency Milestone Date of 07/31/2026 for ESA Consultation Request Package Submitted (Agency Action) has passed by 1 business days
Agency Milestone Date of 07/31/2026 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
Triggered missed date from extending Application deemed complete (Agency Action) within 30 days of its current target date which was 08/08/2026 and extended to 08/24/2026