Permitting Action Modification History
Modifications on 08/03/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 12-21-2021 | 12-21-2021 | --- | Yes |
| Completed application received (Agency Action) | 11-21-2025 | 11-21-2025 | 07-29-2026 | Yes |
| Final decision/agency action (Agency Action) | 10-05-2027 | 10-05-2027 | 09-18-2028 | No |
Modifications on 05/21/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 12-21-2021 | 12-21-2021 | --- | Yes |
| Completed application received (Agency Action) | 11-21-2025 | 11-21-2025 | 06-26-2026 | No |
| Final decision/agency action (Agency Action) | 10-05-2027 | 10-05-2027 | 09-18-2028 | No |
Modifications on 11/14/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 12-21-2021 | 12-21-2021 | --- | Yes |
| Completed application received (Agency Action) | 11-21-2025 | 11-21-2025 | 05-02-2026 | No |
| Final decision/agency action (Agency Action) | 10-05-2027 | 10-05-2027 | 09-18-2028 | No |
Modifications on 03/18/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 12-21-2021 | 12-21-2021 | --- | Yes |
| Completed application received (Agency Action) | 11-21-2025 | 11-21-2025 | --- | No |
| Final decision/agency action (Agency Action) | 10-05-2027 | 10-05-2027 | --- | No |