FAST-41 Missed Date:Right-of-Way Authorization (DOI-BLM): Completed application received (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 07/01/2025 for Completed application received (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Land Management
Agency Status: Cooperating under FAST-41
Status:
In Progress
POC Name:
Jacob Vialpando
POC Title:
Field Manager
POC Email:

Milestones:

Initial application received (Agency Action)
Completed Date:
Completed application received (Agency Action)
  • Monthly Status Report for February 2026:
    On January 27, 2026, BLM completed the Decision Record in line with the Proposed Action found in the joint NTIA and BLM EA EAXX-006-60-3D-1754935958, NANA Region Middle Mile Fiber Optic FAST-41 Project and FONSI. The BLM is now preparing the grant offer package for the right-of-way.
  • Monthly Status Report for January 2026:
    The Bureau of Land Management continues to work through the process and decision requirements for the NEPA and will prepare the grant offer package following completion of that decision. 
  • Monthly Status Report for December 2025:
    The BLM is on track to meet the deadlines for the Right-of-Way (ROW) Authorization. The Environmental Assessment and Finding of No Significant Impact (FONSI) are in the review process, the ROW is dependent upon the outcome of the FONSI.
  • Monthly Status Report for November 2025:
    The application was marked complete by BLM on July 15, 2025.  BLM continues to work on this project.
  • Monthly Status Report for October 2025:
    BLM received the initial SF299 on March 28, 2025 and the application was marked complete by BLM on July 15, 2025. 
  • Monthly Status Report for September 2025:
    BLM received the initial SF299 on March 28, 2025; BLM notified NANA on May 14, 2025, that the application contained deficiencies. NANA responded to those requests on June 18. BLM completed a cursory review of the responses and found that sections were now present; however, upon further review, BLM found that deficiencies still exist. BLM sent the “round 2” deficiency request to NANA on July 2. NANA responded and the application was marked complete by BLM on July 15, 2025.
  • Monthly Status Report for August 2025:
    BLM received the initial SF299 on March 28, 2025; BLM notified NANA on May 14, 2025, that the application contained deficiencies. NANA responded to those requests on June 18 (within the 30-day lockout period). BLM did a cursory review of the responses and found that sections were now present; however, upon further review, BLM found that deficiencies still exist. BLM sent the “round 2” deficiency request to NANA on July 2 and hoped to receive all requested information by July 25. NANA responded to the request quickly and BLM was able to mark the SF299 complete on 07/15/2025.
  • Non-conformance Explanation:
    BLM received the initial SF299 on March 28, 2025; BLM notified NANA on May 14, 2025, that the application contained deficiencies. NANA responded to those requests on June 18 (within the 30-day lockout period). BLM did a cursory review of the responses and found that sections were now present; however, upon further review, BLM found that deficiencies still exist. BLM sent the “round 2” deficiency request to NANA on July 2 and hope to receive all requested information by July 25.
Current Target Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone
Completed application received (Agency Action)
  • Monthly Status Report for February 2026:
    On January 27, 2026, BLM completed the Decision Record in line with the Proposed Action found in the joint NTIA and BLM EA EAXX-006-60-3D-1754935958, NANA Region Middle Mile Fiber Optic FAST-41 Project and FONSI. The BLM is now preparing the grant offer package for the right-of-way.
  • Monthly Status Report for January 2026:
    The Bureau of Land Management continues to work through the process and decision requirements for the NEPA and will prepare the grant offer package following completion of that decision. 
  • Monthly Status Report for December 2025:
    The BLM is on track to meet the deadlines for the Right-of-Way (ROW) Authorization. The Environmental Assessment and Finding of No Significant Impact (FONSI) are in the review process, the ROW is dependent upon the outcome of the FONSI.
  • Monthly Status Report for November 2025:
    The application was marked complete by BLM on July 15, 2025.  BLM continues to work on this project.
  • Monthly Status Report for October 2025:
    BLM received the initial SF299 on March 28, 2025 and the application was marked complete by BLM on July 15, 2025. 
  • Monthly Status Report for September 2025:
    BLM received the initial SF299 on March 28, 2025; BLM notified NANA on May 14, 2025, that the application contained deficiencies. NANA responded to those requests on June 18. BLM completed a cursory review of the responses and found that sections were now present; however, upon further review, BLM found that deficiencies still exist. BLM sent the “round 2” deficiency request to NANA on July 2. NANA responded and the application was marked complete by BLM on July 15, 2025.
  • Monthly Status Report for August 2025:
    BLM received the initial SF299 on March 28, 2025; BLM notified NANA on May 14, 2025, that the application contained deficiencies. NANA responded to those requests on June 18 (within the 30-day lockout period). BLM did a cursory review of the responses and found that sections were now present; however, upon further review, BLM found that deficiencies still exist. BLM sent the “round 2” deficiency request to NANA on July 2 and hoped to receive all requested information by July 25. NANA responded to the request quickly and BLM was able to mark the SF299 complete on 07/15/2025.
  • Non-conformance Explanation:
    BLM received the initial SF299 on March 28, 2025; BLM notified NANA on May 14, 2025, that the application contained deficiencies. NANA responded to those requests on June 18 (within the 30-day lockout period). BLM did a cursory review of the responses and found that sections were now present; however, upon further review, BLM found that deficiencies still exist. BLM sent the “round 2” deficiency request to NANA on July 2 and hope to receive all requested information by July 25.
Current Target Date:
Project

PROJECT WEBSITE: https://www.nanabroadband.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/15/2026

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Commerce

LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

The NANA Regional Corporation, Inc. proposes to implement a high-speed broadband network in the NANA region through the Tribal Broadband Connectivity Program. The proposed ~725-mile fiber optic cable route consists of a combination of terrestrial ground-laid, subsea, trenched, and aerial cable to connect villages across vast distances to the broadband Point of Presence in Kotzebue. The Project plans to bring a fiber-based broadband network capable of providing high-speed internet services to Alaska Native Villages in the NANA Region.

field_status
System Comments
Agency Milestone Date of 07/01/2025 for Completed application received (Agency Action) has passed by 1 business days
Approver Comments
<p>On January 27, 2026, BLM completed the Decision Record in line with the Proposed Action found in the joint NTIA and BLM EA EAXX-006-60-3D-1754935958, NANA Region Middle Mile Fiber Optic FAST-41 Project and FONSI. The BLM is now preparing the grant offer package for the right-of-way.</p>
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
Agency Notified Date
New Milestone
Completed application received (Agency Action)
  • Monthly Status Report for February 2026:
    On January 27, 2026, BLM completed the Decision Record in line with the Proposed Action found in the joint NTIA and BLM EA EAXX-006-60-3D-1754935958, NANA Region Middle Mile Fiber Optic FAST-41 Project and FONSI. The BLM is now preparing the grant offer package for the right-of-way.
  • Monthly Status Report for January 2026:
    The Bureau of Land Management continues to work through the process and decision requirements for the NEPA and will prepare the grant offer package following completion of that decision. 
  • Monthly Status Report for December 2025:
    The BLM is on track to meet the deadlines for the Right-of-Way (ROW) Authorization. The Environmental Assessment and Finding of No Significant Impact (FONSI) are in the review process, the ROW is dependent upon the outcome of the FONSI.
  • Monthly Status Report for November 2025:
    The application was marked complete by BLM on July 15, 2025.  BLM continues to work on this project.
  • Monthly Status Report for October 2025:
    BLM received the initial SF299 on March 28, 2025 and the application was marked complete by BLM on July 15, 2025. 
  • Monthly Status Report for September 2025:
    BLM received the initial SF299 on March 28, 2025; BLM notified NANA on May 14, 2025, that the application contained deficiencies. NANA responded to those requests on June 18. BLM completed a cursory review of the responses and found that sections were now present; however, upon further review, BLM found that deficiencies still exist. BLM sent the “round 2” deficiency request to NANA on July 2. NANA responded and the application was marked complete by BLM on July 15, 2025.
  • Monthly Status Report for August 2025:
    BLM received the initial SF299 on March 28, 2025; BLM notified NANA on May 14, 2025, that the application contained deficiencies. NANA responded to those requests on June 18 (within the 30-day lockout period). BLM did a cursory review of the responses and found that sections were now present; however, upon further review, BLM found that deficiencies still exist. BLM sent the “round 2” deficiency request to NANA on July 2 and hoped to receive all requested information by July 25. NANA responded to the request quickly and BLM was able to mark the SF299 complete on 07/15/2025.
  • Non-conformance Explanation:
    BLM received the initial SF299 on March 28, 2025; BLM notified NANA on May 14, 2025, that the application contained deficiencies. NANA responded to those requests on June 18 (within the 30-day lockout period). BLM did a cursory review of the responses and found that sections were now present; however, upon further review, BLM found that deficiencies still exist. BLM sent the “round 2” deficiency request to NANA on July 2 and hope to receive all requested information by July 25.
Current Target Date:
Response Date
Reporting Agency