Permitting Action Modification History

Complete
BLM completed ROW grant ahead of scheduled April date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 03-28-2025 03-28-2025 --- Yes
Completed application received (Agency Action) 07-01-2025 07-01-2025 07-15-2025 Yes
Final decision/agency action (Agency Action) 04-15-2026 02-09-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 03-28-2025 03-28-2025 --- Yes
Completed application received (Agency Action) 07-01-2025 07-01-2025 07-15-2025 Yes
Final decision/agency action (Agency Action) 04-15-2026 04-15-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 03-28-2025 03-28-2025 --- Yes
Completed application received (Agency Action) 07-01-2025 07-01-2025 --- No
Final decision/agency action (Agency Action) 04-15-2026 04-15-2026 --- No