NANA Regional Broadband Network (NRBN)

PERMITTING DASHBOARD PROJECT POSTING DATE: MARCH 11, 2025

PROJECT WEBSITE: https://www.nanabroadband.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/15/2026

8 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Commerce

LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration

View FAST-41 Postings by Agencies

Description:

The NANA Regional Corporation, Inc. proposes to implement a high-speed broadband network in the NANA region through the Tribal Broadband Connectivity Program. The proposed ~725-mile fiber optic cable route consists of a combination of terrestrial ground-laid, subsea, trenched, and aerial cable to connect villages across vast distances to the broadband Point of Presence in Kotzebue. The Project plans to bring a fiber-based broadband network capable of providing high-speed internet services to Alaska Native Villages in the NANA Region.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete