Rejected

Milestone Extension: Environmental Impact Statement (EIS)

New Project information was submitted by the project sponsor on October 4, 2022, October 14, 2022, and October 27, 2022 in response to stakeholder concerns which included an updated COP and permit applications showing a shift to the location of the BL England substation to an adjacent portion of the same property which formerly housed elements of the BL England Generating Station and adjustment of the row A wind turbine generators (WTGs) as outlined in a joint letter signed

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

On October 4, 2022, the FWS sent FERC a letter requesting additional information on Mountain Valley Pipeline, LLC’s (MVP) Updated Supplement to the Biological Assessment (SBA2). On October 19, 2022, FERC provided FERC’s and the Service’s comments on the SBA2 to MVP.

Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

This milestone is dependent on the EIS ROD milestone in the EIS milestones. The ROD milestone moved due to the DEIS delay. This milestone needs to be 120 days after ROD. The DEIS delay is due to lessee not providing a complete and sufficient Historic Resources Visual Effects Assessment (HRVEA) and Terrestrial Archaeological Resources Assessment (TARA) and Visual Impact Assessment (VIA). Without this data BOEM cannot identify historic properties and assess the effects of the project or conduct necessary Section 106 consultation prior to publication of the draft EIS.