Rejected

Milestone Extension: Section 408 Permit

The applicant had initially requested a review schedule for their Kitty Hawk South project with an early NOI coming in October 2022 with the DEIS NOA occurring much later in 2024 - this timeframe has been extended, with an NOA date in Feb 2026 and a ROD date in Dec 2026.  USACE milestones were adjusted accordingly.

Milestone Extension: Environmental Impact Statement (EIS)

New Project information was submitted by the project sponsor on October 4, 2022, October 14, 2022, and October 27, 2022 in response to stakeholder concerns which included an updated COP and permit applications showing a shift to the location of the BL England substation to an adjacent portion of the same property which formerly housed elements of the BL England Generating Station and adjustment of the row A wind turbine generators (WTGs) as outlined in a joint letter signed

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

On October 4, 2022, the FWS sent FERC a letter requesting additional information on Mountain Valley Pipeline, LLC’s (MVP) Updated Supplement to the Biological Assessment (SBA2). On October 19, 2022, FERC provided FERC’s and the Service’s comments on the SBA2 to MVP.